(a) A contractor who asserts a claim of breach of contract under Government Code, Chapter 2260, must file a notice of the claim as provided under this section.
(b) The notice of claim shall:
(1) be written and signed by the contractor or the contractor's authorized representative;
(2) be delivered by hand, certified mail return receipt requested, or other verifiable delivery service, to the agency officer who is designated in the contract to receive a notice of claim of breach of contract under Government Code, Chapter 2260; if no person is designated in the contract, then the notice shall be delivered to the comptroller; and
(3) state in detail:
(c) In addition to the mandatory contents of the notice of claim that are required under subsection (b) of this section, the contractor may submit supporting documentation or other tangible evidence to facilitate the agency's evaluation of the contractor's claim.
(d) The notice of claim shall be delivered not later than 180 days after the date of the event that the contractor cites as the basis of the claim.
Source Note: The provisions of this §1.365 adopted to be effective November 29, 2001, 26 TexReg 9631