(a) Commitment or Reservation of Funds. The Administrator must submit true and correct information, certified as such, with a request for the Commitment of Funds as described in paragraphs (1) - (12) of this subsection:
(1) Head of Household name and address of housing unit for which assistance is being requested;
(2) A budget that includes the amount of Activity funds specifying the acquisition cost, construction costs, contractor fees, and developer fees, as applicable. A maximum of five percent of hard construction costs for contingency items, proposed Match to be provided, evidence that Activity Cost limitations are not exceeded, and evidence that any duplication of benefit is addressed;
(3) Verification of environmental clearance;
(4) A copy of the Household's intake application on a form prescribed by the Department;
(5) Certification of the income eligibility of the Household signed by the Administrator and all Household members age 18 or over, and including the date of the income eligibility determination. All documentation used to determine the income of the Household must be provided;
(6) Project cost estimates, construction contracts, and other construction documents necessary, in the Department's sole determination, to ensure applicable property standard requirements will be met at completion;
(7) Identification of Lead-Based Paint (LBP) if site remediation is needed;
(8) Executed sales contract and documentation that the first lien mortgage meets the eligibility requirements;
(9) Evidence that the housing unit will be located outside the 100-year floodplain;
(10) If applicable, documentation to address or resolve any potential conflict of interest, Identity of Interest, duplication of benefit, or floodplain mitigation;
(11) Appraisal, which includes post construction improvements; and
(12) Any other documentation necessary to evidence that the Activity meets the program requirements.
(b) Construction Loan closing. The Administrator must submit the documents described in paragraphs (1) - (2) of this subsection, with a request for the preparation of loan closing with the request for the Commitment of Funds:
(1) A title commitment to issue a title policy that evidences the property will transfer with no tax lien, child support lien, mechanic's or materialman's lien or any other restrictions or encumbrances that impair the good and marketable nature of title to the ownership interest and that the definition of Homeownership will be met. The effective date of the title commitment must be no more than 60 days prior to the date of project submission. Commitments that expire prior to execution of closing must be updated at closing and must not have any adverse changes in order to close; and
(2) Within 90 days after the loan closing date, the Administrator must submit to the Department the original recorded deed of trust and transfer of lien, if applicable. Failure to submit these documents within 90 days after the loan closing date will result in the Department withholding payment for disbursement requests.
(c) Disbursement of funds. The Administrator must comply with the requirements described in paragraphs (1) - (11) of this subsection, for a request for disbursement of funds to reimburse eligible costs incurred. Submission of documentation related to the Administrator compliance with requirements described in paragraphs (1) - (11) of this subsection may be required with a request for disbursement:
(1) For construction costs, an interim construction binder advance endorsement not older than the date of the last disbursement of funds or 45 days, whichever is later. For release of retainage a down date endorsement to the mortgagee policy issued to the homebuyer dated at least 40 days after the Construction Completion Date;
(2) If required or applicable, a maximum of 50 percent of Direct Activity Costs for an Activity may be drawn before providing evidence of Match. Thereafter, each Administrator must provide evidence of Match, including the date of provision, in accordance with the percentage of Activity funds disbursed;
(3) Property inspections, including photographs of the front, back, and side elevations of the housing unit and at least one picture of each of the kitchen, family room, each bedroom and each bathroom with date and property address reflected on each photo. The inspection must be signed and dated by the inspector and Administrator or Developer;
(4) Certification that its fiscal control and fund accounting procedures are adequate to assure the proper disbursal of, and accounting for, funds provided, no Person that would benefit from the award of HOME funds has provided a source of Match or has satisfied the Applicant's cash reserve obligation or made promises in connection therewith; that each request for disbursement of HOME funds is for the actual cost of providing a service and that the service does not violate any conflict of interest provisions;
(5) Original, executed, legally enforceable loan documents containing remedies adequate to enforce any applicable affordability requirements. Original documents must evidence that such agreements have been recorded in the real property records of the county in which the housing unit is located and the original documents must be returned, duly certified as to recordation by the appropriate county official;
(6) Expenditures must be allowable and reasonable in accordance with federal, state, and local rules and regulations. The Department shall determine the reasonableness for expenditures submitted for reimbursement. The Department may request Administrator or Developer to make modifications to the disbursement request and is authorized to modify the disbursement procedures set forth herein and to establish such additional requirements for payment of HOME funds to Administrator or Developer as may be necessary or advisable for compliance with all Program Requirements;
(7) Table funding requests must be submitted to the Department with complete documentation no later than 14 days prior to the anticipated loan closing date. Such a request must include a draft settlement statement, title company payee identification information, the Administrator or Developer's authorization for disbursement of funds to the title company, request letter from title company to the Comptroller of Public Accounts with bank account wiring instructions, and invoices for costs being paid at closing;
(8) Include the withholding of ten percent of hard construction costs for retainage. Retainage will be held until at least 40 days after the Construction Completion Date;
(9) For final disbursement requests, submission of documentation required for Activity completion reports;
(10) The final request for disbursement must be submitted to the Department with support documentation no later than 60 days after the termination date of the Contract in order to remain in compliance with Contract and eligible for future funding. The Department shall not be obligated to pay for costs incurred or performances rendered after the termination date of a Contract; and
(11) For costs associated with insurance policies, including title policies and homeowner's insurance policies, charged as Activity costs, evidence of payment of the cost must be submitted with the retainage request.
Source Note: The provisions of this §23.62 adopted to be effective March 28, 2024, 49 TexReg 1902