Administrative Draw request. Administrative Draw requests are funded out of the portion of the Contract budget specified for administrative cost (administration line item of the Contract budget). These costs are not directly associated with an Activity. The administration line item will be disbursed as described in paragraphs (1) - (8) of this section:
(1) Threshold 1. The initial administrative Draw request allows up to 10% of the administration line item may be drawn down prior to the start of any project Activity included in the Performance Statement of the Contract (provided that all Pre-Draw requirements, as described in the Contract, for administration have been met). Subsequent administrative funds will be reimbursed in proportion to the percentage of the work that has been completed as identified in paragraphs (2) - (8) of this section.
(2) Threshold 2. Up to an additional 15% (25% of the total) of the administration line item to be drawn down after a start of project Activity has been demonstrated. For the purposes of this threshold, if Davis- Bacon labor standards are required for a given Program Activity, the "start of project Activity" is evidenced by the submission of a start of construction form. If labor standards are not required on a given project Activity that has commenced (and for which reimbursement is being sought), the submission of a Draw request that includes sufficient back-up documentation for expenses of non- administrative project Activities evidences a start of project Activity. Direct Delivery Costs charges will not constitute a start of project Activity.
(3) Threshold 3. Up to an additional 25% (50% of the total) of the administration line item may be drawn down after compliance with the 20-month threshold requirement has been demonstrated as described in §25.10 of this chapter (relating to Expenditure Thresholds and Closeout Requirements).
(4) Threshold 4. Up to an additional 25% (75% of the total) of the administration line item may be drawn down after compliance with the 32-month threshold requirement has been demonstrated as described in §25.10 of this chapter.
(5) Threshold 5. Up to an additional 15% (90% of the total) of the administration line item may be drawn down after compliance with the 44-month threshold requirement has been demonstrated as described in §25.10 of this chapter.
(6) Threshold 6. Up to an additional 5% (95% of the total) of the administration line item may be drawn down upon receipt of all required close-out documentation.
(7) Threshold 7. The final 5% (100% of the total), less any administrative funds reserved for audit costs as noted on the Project Completion Report of the administration line item, may be drawn down following receipt of the programmatic close-out letter issued by Department.
(8) Threshold 8. Any funds reserved for audit costs will be released upon completion and submission of an acceptable audit. Only the portion of audit expenses reasonably attributable to the Contract is eligible.
Source Note: The provisions of this §25.9 adopted to be effective January 2, 2022, 46 TexReg 9009