(a) Application. This rule applies to all electric utilities.
(b) Reports. By May 1st of each year, an electric utility shall file with the commission a report that contains the information described in subsection (c) of this section for the previous calendar year.
(c) The utility shall include in the report a description of the utility's activities related to:
(1) Identifying areas in its service territory that are susceptible to damage during severe weather and hardening transmission and distribution facilities in those areas;
(2) Vegetation management; and
(3) Inspecting distribution poles.
(d) Each electric utility shall include in a report required under subsection (b) of this section a summary of the utility's activities related to preparing for emergency operations.
Source Note: The provisions of this §25.94 adopted to be effective January 3, 2010, 35 TexReg 91