(a) In addition to determining the engineering feasibility of a project, the commission shall also determine the economic feasibility of each proposed bond issue, bond amendment, and extension of time application for a bond issue. The staff of the commission shall use the following sections in making economic feasibility analysis. In its written recommendations to the commission, which analyze the particular application, the staff shall always address the economic feasibility.
(b) Economic feasibility is the determination of whether the land values, existing improvements, and projected improvements in the district will be sufficient to support a reasonable tax rate for debt service payments for existing and proposed bond indebtedness while maintaining competitive utility rates. Utility rates that do not exceed the rates of the largest city in the geographic area in which the district is located are conclusively deemed to be competitive. Economic feasibility is influenced by many factors and varies widely depending on economic conditions, the real estate market, the number of competing projects, and geographic location.
(c) Projected debt service tax rate is the tax rate required to meet the projected annual debt service requirement using projected assessed valuations and an appropriate tax collection rate. The projected annual debt service requirement shall include the previous and proposed debt. The projected debt service tax rate for any bond issue shall be shown in the cash flow table as a level or decreasing tax rate.
(d) No-growth debt service tax rate is the tax rate required to meet projected annual debt service requirements using the current assessed value and a 100% tax collection rate. The current value is determined by either:
(1) the most recent certificate of assessed valuation from the central appraisal district; or
(2) a certificate of estimated assessed valuation from the central appraisal district. Projected annual debt service requirements shall include the previous and proposed debt. The no-growth debt service tax rate for any bond issue shall be shown on the cash flow table as a level or decreasing tax rate.
(e) Combined no-growth tax rate is the sum of the following:
(1) no-growth debt service tax rate of the district;
(2) projected no-growth debt service tax rate of all overlapping entities specifically attributable to water, wastewater, drainage, or recreational facilities that are smaller in size than a county, and for roads if the entity is a road district or road utility district smaller in size than a county commissioner's precinct. (In other words, for road districts or road utility districts that are as large as one county commissioner's precinct, the road district tax is not counted.);
(3) an equivalent surcharge tax rate for water and wastewater surcharge, if any;
(4) city tax rate specifically attributable to water, sewage, drainage, and recreational facilities if the district is located within a city;
(5) current or proposed district or overlapping maintenance tax levy, if any;
(6) contract tax, if any; and
(7) less any equivalent tax rebate or other payments.
(f) Combined projected tax rate is the sum of the following:
(1) projected debt service tax rate of the district;
(2) projected debt service tax rate of all overlapping entities specifically attributable to water, wastewater, drainage, recreational facilities, and for roads if the entity is a road district or road utility district smaller in size than a county commissioner's precinct;
(3) an equivalent surcharge tax rate for water and wastewater surcharge, if any;
(4) city tax rate specifically attributable to water, sewage, drainage, and recreational facilities if the district is located within a city;
(5) current or proposed district or overlapping maintenance tax levy, if any;
(6) contract tax, if any; and
(7) less any equivalent tax rebate or other payment.
(g) A surcharge is a flat charge in addition to rates imposed on residents receiving water and/or wastewater service from resources of a city or other entity and supplied through district facilities. Surcharge revenues are placed in the district's debt service fund and are intended to be used to meet the debt service requirement on the district's bonds.
(h) For districts collecting surcharge revenues, the equivalent surcharge tax rate shall be calculated as follows.
(1) For residential development with similar house prices:
(2) For mixed-use development and diverse house prices:
(3) For purposes of this calculation, no adjustments shall be made for projected collection rate of the surcharge, interest earnings on the surcharge account, or other factors.
(i) For districts receiving a rebate for taxes paid to a city or other entity for water, wastewater, drainage, recreational, or road service, the equivalent tax rebate shall be calculated as follows:
(j) The assessed value is the appraised value after considering exemptions and special valuations and is the amount to which the tax rate is applied to determine the total tax levy.
(k) For a district's first bond issue, the following paragraphs apply except that paragraphs (5), (6), (8), and (10) of this subsection are only applicable to a district that has a developer as defined by Texas Water Code (TWC), §49.052(d).
(1) The district shall provide the current and projected tax rates of all entities levying or proposing to levy taxes on land within the district and a comparison of such taxes with the total tax levy on all competing projects in the same market area, as defined in the market study, if applicable, shall be provided.
(2) A cash flow analysis to determine the projected debt service revenue and projected tax rate shall be provided. It should include the following assumptions.
(3) The combined projected tax rate must not exceed the following:
(4) The combined no-growth tax rate must not exceed the following:
(5) The following apply to the central appraisal district certificate.
(6) At the time of commission approval, the following shall apply:
(7) At least 25% of the projected value of houses, buildings, and/or other improvements shown in the projected tax rate calculations must be completed prior to advertising for the bond issue. The projections used to satisfy this section shall also be used in the calculations required by paragraphs (2) and (3) of this subsection.
(8) For bonds supported by taxes, a written agreement must be executed between the district and the developer and any other landowner and their respective lenders receiving proceeds of the bonds that permanently waives the right to claim agricultural, open-space, timberland, or inventory valuation for any land, homes, or buildings that they own in the district with respect to taxation by the district. The agreement shall be binding for 30 years on such developer, other landowners, their respective lenders, any related or affiliated entities, and their successors and assignees, unless such exemptions were in effect at the time of the commission's approval of the bond issue and such exemptions were shown in the projected tax rate calculations. Such developer, landowners, and lenders shall record covenants running with the land to such effect, which shall not be modified or released without written authorization of the commission, and shall provide recorded copies to the commission at the time of filing a bond application. If written agreements by owners of developable property who are not receiving bond proceeds are not voluntarily provided, and the ratio of the assessed valuation of their property to the district's total certified assessed valuation exceeds 10% for any individual or 20% for all combined, the feasibility analysis of the bond issue will be based on a reduced value for such property if not already on the tax rolls at a minimal value.
(9) One or more of the requirements in paragraphs (1) - (8) of this subsection may be waived for good cause by commission order if all of the facilities proposed under a bond issue application are essential because of valid orders, permits, or actions against the district by a governmental agency or court. If only a portion of the bond issue is for facilities essential because of valid orders, permits, or actions against the district by a governmental agency or court and if a waiver of any of the requirements is requested, all nonessential projects may be deleted from the bond issue if not feasible under the other provisions of these rules.
Cont'd...