(a) Easement protection. No solid waste unloading, storage, disposal, or processing operations shall occur within any easement, buffer zone, or right-of-way that crosses the site. No solid waste disposal shall occur within 25 feet of the center line of any utility line or pipeline easement, unless otherwise authorized by the executive director. All pipeline and utility easements must be clearly marked with posts that extend at least six feet above ground level, spaced at intervals no greater than 300 feet.
(b) Buffer zones. A minimum separating distance shall be maintained between solid waste processing and disposal activities within and adjacent to the facility boundary on property owned or controlled by the owner or operator as determined by the requirements of §330.543 of this title (relating to Easements and Buffer Zones). The buffer zone must provide for safe passage for fire-fighting and other emergency vehicles.
Source Note: The provisions of this §330.141 adopted to be effective March 27, 2006, 31 TexReg 2502