(a) Purpose. The executive administrator will issue a Certificate of Approval (certificate) upon completion of all work under each prime construction contract.
(b) Final prime construction contract. A certificate will be issued at the completion of all work under the final prime construction contract. This certificate will be transmitted to the Applicant with a statement that the project and the Board's inspection process are complete.
Source Note: The provisions of this §371.85 adopted to be effective June 10, 2020, 45 TexReg 3863