(a) Within 60 days of Applicant's receipt of the certificate of approval for the final prime construction contract and the final inspection report, the Applicant shall submit a final accounting and a final funds requisition form.
(b) After the final accounting, the executive administrator shall notify the Applicant if remaining surplus funds exist and advise the Applicant that the remaining surplus funds may be used in a manner as approved by the executive administrator.
Source Note: The provisions of this §375.106 adopted to be effective September 8, 2010, 35 TexReg 8126; amended to be effective July 30, 2012, 37 TexReg 5615; amended to be effective July 4, 2016, 41 TexReg 4853; amended to be effective March 18, 2019, 44 TexReg 1445