(a) Fees. In addition to the fee for each injection well required by §3.78 of this title (relating to Fees and Financial Security Requirements), the following non-refundable fees must be remitted to the Commission with the application:
(1) Base application fee. (A) The applicant must pay to the Commission an application fee of $50,000 for each permit application for a geologic storage facility. (B) The applicant must pay to the Commission an application fee of $25,000 for each application to amend a permit for a geologic storage facility.
(2) Injection fee. The operator must pay to the Commission an annual fee of $0.025 per metric ton of CO 2 injected into the geologic storage facility.
(3) Post-injection care fee. The operator must pay to the Commission an annual fee of $50,000 each year the operator does not inject into the geologic storage facility until the director has authorized storage facility closure.
(b) Financial responsibility.
(1) A person to whom a permit is issued under this subchapter must provide annually to the director evidence of financial responsibility that is satisfactory to the director. The owner or operator must demonstrate and maintain financial responsibility for corrective action, injection well plugging, post-injection storage facility care and storage facility closure, and emergency and remedial response until the director has provided written verification that the director has determined that the facility has reached the end of the post-injection storage facility care period.
(2) In determining whether the person is financially responsible, the director must rely on: (A) the person's most recent audited annual report filed with the U. S. Securities and Exchange Commission under Section 13 or 15(d), Securities Exchange Act of 1934 (15 U.S.C. Section 78m or 78o(d)); and (B) the person's most recent quarterly report filed with the U. S. Securities and Exchange Commission under Section 13 or 15(d), Securities Exchange Act of 1934 (15 U.S.C. Section 78m or 78o(d)); or (C) if the person is not required to file such a report, the person's most recent audited financial statement. The date of the audit must not be more than one year before the date of submission of the application to the director.
(3) The applicant's demonstration of financial responsibility must account for the entire AOR, regardless of whether corrective action in the AOR is phased.
(c) Financial assurance. The director shall consider and approve the applicant's demonstration of financial responsibility for all the phases of the geologic sequestration project, including the post-injection storage facility care and closure phase and the plugging phase, prior to issuance of a geologic storage injection well permit.
(1) Injection and monitoring wells. The owner or operator must comply with the requirements of §3.78 of this title for all monitoring wells that penetrate the base of usable quality water and this subsection for all injection wells.
(2) Geologic storage facility. (A) The applicant must include in an application for a geologic storage facility permit: (i) a detailed written estimate, in current dollars, of the cost necessary to perform corrective action on wells in the area of review, plugging of injection wells, post-injection monitoring and closure of the facility, and emergency and remedial response that shows all assumptions and calculations used to develop the estimate; (ii) a copy of the form of the bond or letter of credit that will be filed with the Commission; and (iii) information concerning the issuer of the bond or letter of credit including the issuer's name and address and evidence of authority to issue bonds or letters of credit in Texas. (B) A geologic storage facility shall not receive CO 2 until a bond or letter of credit in an amount approved by the director under this subsection and meeting the requirements of this subsection as to form and issuer has been filed with and approved by the director. (C) The determination of the amount of financial assurance for a geologic storage facility is subject to the following requirements: (i) The director must approve the dollar amount of the financial assurance. The amount of financial assurance required to be filed under this subsection must be equal to or greater than the maximum amount necessary to perform corrective action, emergency response, and remedial action, post-injection monitoring and site care, and closure of the geologic storage facility, including plugging of wells, at any time during the permit term in accordance with all applicable state laws, Commission rules and orders, and the permit. The cost estimate must be performed for each phase separately and must be based on the costs to the Commission of hiring a third party to perform the required activities. A third party is a party who is not within the corporate structure of the owner or operator; (ii) A qualified professional engineer licensed by the State of Texas, as required under Occupations Code, Chapter 1001, relating to Texas Engineering Practice Act, must prepare or supervise the preparation of a written estimate of the highest likely amount necessary to close the geologic storage facility. The owner or operator must submit to the director the written estimate under seal of a qualified licensed professional engineer, as required under Occupations Code, Chapter 1001, relating to Texas Engineering Practice Act; and (iii) The Commission may use the proceeds of financial assurance filed under this subsection to pay the costs of plugging any well or wells at the facility if the financial assurance for plugging costs filed with the Commission is insufficient to pay for the plugging of such well or wells. (D) Bonds and letters of credit filed in satisfaction of the financial assurance requirements for a geologic storage facility must comply with the following standards as to issuer and form. (i) The issuer of any geologic storage facility bond filed in satisfaction of the requirements of this subsection must be a corporate surety authorized to do business in Texas. The form of bond filed under this subsection must provide that the bond be renewed and continued in effect until the conditions of the bond have been met or its release is authorized by the director. (ii) Any letter of credit filed in satisfaction of the requirements of this subsection must be issued by and drawn on a bank authorized under state or federal law to operate in Texas. The letter of credit must be an irrevocable, standby letter of credit subject to the requirements of Texas Business and Commerce Code, §§5.101 - 5.118. The letter of credit must provide that it will be renewed and continued in effect until the conditions of the letter of credit have been met or its release is authorized by the director. (iii) The qualifying financial responsibility instruments must comprise protective conditions of coverage. Protective conditions of coverage must include at a minimum cancellation, renewal, and continuation provisions; specifications on when the provider becomes liable following a notice of cancellation if there is a failure to renew with a new qualifying financial instrument; and requirements for the provider to meet a minimum rating, minimum capitalization, and ability to pass the bond rating when applicable. (I) Cancellation. An owner or operator must provide that its financial instrument may not cancel, terminate, or fail to renew except for failure to pay such financial instrument. If there is a failure to pay the financial instrument, the financial institution may elect to cancel, terminate, or fail to renew the instrument by sending notice by certified mail to the owner or operator and the director. The cancellation must not be final until at least 120 days after the Commission receives the cancellation notice. The owner or operator must provide an alternate financial responsibility demonstration within 60 days of notice of cancellation, and if an alternate financial responsibility demonstration is not acceptable or possible, any funds from the instrument being cancelled must be released within 60 days of notification by the director. (II) Renewal. If a financial instrument expires, the owner or operator must renew the financial instrument for the entire term of the geologic storage project. The instrument may be automatically renewed as long as the operator has the option of renewal at the face amount of the expiring instrument. The automatic renewal of the instrument must, at a minimum, provide the holder with the option of renewal at the face amount of the expiring financial instrument. (III) Financial instrument to remain in effect. Cancellation, termination, or failure to renew shall not occur and the financial instrument shall remain in full force and effect if on or before the date of expiration: (-a-) the director deems the facility abandoned; (-b-) the permit is terminated or revoked or a new permit is denied; (-c-) closure is ordered by the director or a United States district court or other court of competent jurisdiction; (-d-) the owner or operator is named as debtor in a voluntary or involuntary proceeding under Title 11 (Bankruptcy), U.S. Code; or (-e-) the amount due is paid. (E) During the active life of the geologic storage project, the owner or operator must adjust the cost estimate for inflation within 60 days prior to the anniversary date of the establishment of the financial instruments used to comply with paragraph (2)(C)(i) of this subsection and provide this adjustment to the director. The owner or operator must also provide to the director written updates of adjustments to the cost estimate within 60 days of any amendments to the area of review and corrective action plan, the injection well plugging plan, the post-injection storage facility care and closure plan, and the emergency and remedial response plan. (F) The owner or operator of a geologic storage facility must provide to the director, and the director must approve, annual written updates of the cost estimate to increase or decrease the cost estimate to account for any changes to the AOR and corrective action plan, the emergency response and remedial action plan, the injection well plugging plan, and the post-injection storage facility care and closure plan. The Director must approve any decrease or increase to the initial cost estimate. During the active life of the geologic storage project, the owner or operator must revise the cost estimate no later than 60 days after the director has approved the request to modify the AOR and corrective action plan, the injection well plugging plan, the post-injection storage facility care and closure plan, and the emergency and response plan, if a change in any of these plans increases the cost. If a change to a plan decreases the cost, any withdrawal of funds must be approved by the director. Any decrease to the value of a financial assurance instrument must first be approved by the director. The revised cost estimate must be adjusted for inflation as specified at paragraph (2)(E) of this subsection. The owner or operator must provide to the director, within 60 days of notification by the director, an adjustment of the cost estimate if the director determines during the annual evaluation of the qualifying financial responsibility instruments that the most recent demonstration is no longer adequate to cover the cost of corrective action, injection well plugging and post-injection storage facility care and closure, and emergency and remedial response. (G) Whenever the current cost estimate increases to an amount greater than the face amount of a financial instrument currently in use, the owner or operator, within 60 days after the increase, must either cause the face amount to be increased to an amount at least equal to the current cost estimate and submit evidence of such increase to the director or obtain other financial responsibility instruments to cover the increase. Whenever the current cost estimate decreases, the face amount of the financial assurance instrument may be reduced to the amount of the current cost estimate only after the operator has received written approval from the director. (H) The requirement to maintain adequate financial responsibility is directly enforceable regardless of whether the requirement is a condition of the permit. (i) The owner or operator must maintain financial responsibility until: (I) the director receives and approves the completed post-injection storage facility care and closure plan; and (II) the director issues the certificate of closure. (ii) The owner or operator may be released from a financial instrument in the following circumstances: (I) The owner or operator has completed the phase of the geologic storage project for which the financial instrument was required and has fulfilled all its financial obligations as determined by the director, including obtaining financial responsibility for the next phase of the geologic storage project, if required; or (II) The owner or operator has submitted a replacement financial instrument and received written approval from the director accepting the new financial instrument and releasing the owner or operator from the previous financial instrument.
(3) The director may consider allowing the phasing in of financial assurance for only corrective action based on project-specific factors.