(a) The owner of a building or facility with a project required to be registered under §68.21 must obtain an inspection by a registered accessibility specialist no later than one year from the date of the completion of construction.
(b) A request for inspection must be in writing and submitted to a registered accessibility specialist.
(c) The owner, the owner's designated agent, or an individual representing the owner is required to be physically onsite with the registered accessibility specialist during the inspection. A physical or electronic signature must be provided by the owner or designated agent who was present during the inspection on a form prescribed by the department.
Source Note: The provisions of this §68.41 adopted to be effective August 31, 2023, 48 TexReg 4642