(a) Each rail transit agency shall develop a corrective action plan for:
(1) results from investigations in which identified causal and contributing factors are determined by the rail transit agency or the department to require corrective actions; and
(2) findings from safety and security reviews performed by the department that require corrective action.
(b) Each corrective action plan must identify the action to be taken by the rail transit agency, an implementation schedule, and the individual or department responsible for implementation of the plan.
(c) The department will review the corrective action plan within 30 days after the date of receipt. If a plan is not approved, the department will work with the rail transit agency to develop appropriate corrective action plans.
(d) The rail transit agency shall provide the department with verification that corrective actions have been implemented, as described in the corrective action plan, or that proposed alternate actions will be implemented, subject to department review and approval.
(e) If the rail transit agency disputes the department's decision related to a corrective action plan, the rail transit agency shall submit an application for administrative review under §7.93 of this subchapter (relating to Administrative Review) not later than 30 days after the date of receipt of the written decision.
(f) Failure to complete a corrective action plan is a violation under this subchapter.
Source Note: The provisions of this §7.91 adopted to be effective February 19, 2020, 45 TexReg 1041